LA Metro Construction Committee · Feb 18, 2026
Construction Committee on 1:00 PM, Wednesday49 min1 official identified1 public speaker10 agenda itemsVideo: Granicus
The longest item after routine business: Program management project status, 20 min of this 49 min meeting.
Click any time stamp on this page to jump the video there.
Agenda · 10 itemsShowHide
- 2:25VERMONT TRANSIT CORRIDOR BRT PROJECT- CONSTRUCTION MANAGER/GENERAL CONTRACTOR AUTHORIZE the Chief Executive Officer to: A. AWARD Contract No. PS135255000 to Griffith Company, for the Vermont Transit Corridor Bus Rapid Transit (BRT) Project (Project) Construction Manager/General Contractor (CM/GC) Phase 1, in the amount of $4,792,452 for Preconstruction Services, subject to the resolution of any properly submitted protest(s), if any; B. ESTABLISH a Preconstruction Budget for the Project in an amount of $198,460,000; and C. NEGOTIATE and EXECUTE all project-related agreements and modifications within the authorized Preconstruction Budget.
- 6:43Jacquelyn Dupont-Walker was called to speakImelda Padilla was called to speakFernando Dutra was called to speakJacquelyn Dupont-Walker was called to speakFernando Dutra was called to speakFernando Dutra was called to speakJacquelyn Dupont-Walker was called to speakPublic Speaker was called to speak
- 12:14VERMONT TRANSIT CORRIDOR BRT PROJECT- CONSTRUCTION MANAGER/GENERAL CONTRACTOR AUTHORIZE the Chief Executive Officer to: A. AWARD Contract No. PS135255000 to Griffith Company, for the Vermont Transit Corridor Bus Rapid Transit (BRT) Project (Project) Construction Manager/General Contractor (CM/GC) Phase 1, in the amount of $4,792,452 for Preconstruction Services, subject to the resolution of any properly submitted protest(s), if any; B. ESTABLISH a Preconstruction Budget for the Project in an amount of $198,460,000; and C. NEGOTIATE and EXECUTE all project-related agreements and modifications within the authorized Preconstruction Budget. Moved by 0, no second required.
- 12:24VERMONT TRANSIT CORRIDOR BRT PROJECT- CONSTRUCTION MANAGER/GENERAL CONTRACTOR AUTHORIZE the Chief Executive Officer to: A. AWARD Contract No. PS135255000 to Griffith Company, for the Vermont Transit Corridor Bus Rapid Transit (BRT) Project (Project) Construction Manager/General Contractor (CM/GC) Phase 1, in the amount of $4,792,452 for Preconstruction Services, subject to the resolution of any properly submitted protest(s), if any; B. ESTABLISH a Preconstruction Budget for the Project in an amount of $198,460,000; and C. NEGOTIATE and EXECUTE all project-related agreements and modifications within the authorized Preconstruction Budget. (Approved)
- 12:26LINK UNION STATION PROJECT PRECONSTRUCTION BUDGET AUTHORIZE the Chief Executive Officer to: A. AMEND the Preconstruction Budget for the Link Union Station Phase A Project (Project) by $210.06 million, from $297.82 million to $507.88 million, to fund early work, third party agreements, real estate acquisitions, and related support costs; and B. NEGOTIATE and EXECUTE all project-related agreements and modifications to existing contracts within the authorized Preconstruction Budget.
- 13:03Roll Call: 6 members present, 1 members absent, 0 members excused.
- 27:15LINK UNION STATION PROJECT PRECONSTRUCTION BUDGET AUTHORIZE the Chief Executive Officer to: A. AMEND the Preconstruction Budget for the Link Union Station Phase A Project (Project) by $210.06 million, from $297.82 million to $507.88 million, to fund early work, third party agreements, real estate acquisitions, and related support costs; and B. NEGOTIATE and EXECUTE all project-related agreements and modifications to existing contracts within the authorized Preconstruction Budget. Moved by 0, no second required.
- 27:22LINK UNION STATION PROJECT PRECONSTRUCTION BUDGET AUTHORIZE the Chief Executive Officer to: A. AMEND the Preconstruction Budget for the Link Union Station Phase A Project (Project) by $210.06 million, from $297.82 million to $507.88 million, to fund early work, third party agreements, real estate acquisitions, and related support costs; and B. NEGOTIATE and EXECUTE all project-related agreements and modifications to existing contracts within the authorized Preconstruction Budget. (Approved)
- 27:28PROGRAM MANAGEMENT PROJECT STATUS RECEIVE AND FILE this Program Management Project Status Report that summarizes capital program performance through November 2025.
- 47:49GENERAL PUBLIC COMMENT RECEIVE General Public Comment
What happened
Each sentence checked against the transcript.
- The committee took up item 8, the Vermont Transit Corridor BRT Project, and staff presented the recommendation to award a Construction Manager General Contractor Phase 1 contract to Griffith Company.2:23
- For item 9, staff presented a proposed $210 million amendment to the Link Union Station pre-construction budget, bringing it to $508 million.12:32
- Item 9 was announced as “deemed approved unanimously by the committee” after no public comments were made on it.27:16
- Staff presented item 10, the program management project status report, covering projects including Purple Line Extension, I-5 North, 105 Express Lanes and Vermont.27:43
- After no public comments on item 10, the report was announced as a receive and file.47:40
Who spoke
1 official identified · talk time, most first.
- James ButtsChair · Committee · 0.3 minFirst speaks at 47:24
Public comment: 1 speaker.
How we count
Each summary sentence is checked against the transcript before it is published; in a blind check, 98 of 100 sentences were right. A voice gets an official’s name only when two AI readers and a code check agree, so the minutes undercount and are not attendance. Officials only: members of the public are counted, never named, shown or quoted, and full transcripts aren’t published because they can carry their names. More on how we know
Cite this page
Hamlet, “LA Metro Construction Committee, Feb 18, 2026: Los Angeles.” https://cities.myhamlet.com/la/metro-construction/meetings/2026-02-18. Data as of Oct 9, 2026 (version d14b03c); meeting of Feb 18, 2026.