LA Metro Construction Committee · Apr 15, 2026

Construction Committee on 1:00 PM, Wednesday45 min0 public speakers9 agenda itemsVideo: Granicus

The longest item after routine business: Office of the inspector general construction change order spot checks, 18 min of this 45 min meeting.

  • Nov 251
  • Jan 261
  • Feb 261
  • Mar 261
  • Apr 261
  • May 261
  • Jul 261
  • Sep 261
8 meetings, all transcribed, Oct 24, 2025 to Oct 2, 2026.This meeting: Apr 15, 2026
0:00:0045:00

Click any time stamp on this page to jump the video there.

Agenda · 9 itemsShowHide
  1. 1:38Roll Call: 6 members present, 1 members absent, 0 members excused.1 min
  2. 3:03APPROVE Consent Calendar Items: 10, 11, and 12. Consent Calendar items are approved by one motion unless held by a Director for discussion and/or separate action.under 1 min
  3. 3:37Motion to Approve APPROVE Consent Calendar Items: 10, 11, and 12. Consent Calendar items are approved by one motion unless held by a Director for discussion and/or separate action. Moved by 0, no second required.under 1 min
  4. 3:41Vote to Approve APPROVE Consent Calendar Items: 10, 11, and 12. Consent Calendar items are approved by one motion unless held by a Director for discussion and/or separate action. (Approved)under 1 min
  5. 3:43PROGRAM MANAGEMENT QUARTERLY CHANGE REPORT RECEIVE AND FILE status report on Program Management Quarterly Changes.2 min
  6. 6:24Jacquelyn Dupont-Walker was called to speakFernando Dutra was called to speakJacquelyn Dupont-Walker was called to speakJacquelyn Dupont-Walker was called to speakFernando Dutra was called to speakJacquelyn Dupont-Walker was called to speakMonica Benavides was called to speakJacquelyn Dupont-Walker was called to speakFernando Dutra was called to speakMonica Benavides was called to speak6 min
  7. 13:13OFFICE OF THE INSPECTOR GENERAL CONSTRUCTION CHANGE ORDER SPOT CHECKS RECEIVE AND FILE Office of the Inspector General Construction Change Order Spot Check Report for the period December 1, 2025, to February 28, 2026.18 min
  8. 31:24CALTRANS QUARTERLY REPORT RECEIVE the quarterly oral report on the status of the Caltrans construction projects.13 min
  9. 45:05GENERAL PUBLIC COMMENT RECEIVE General Public Comment

What happened

Each sentence checked against the transcript.

  1. The committee took up a consent calendar of items 10, 11, and 12, which was moved and seconded; no public comments were made on it.3:02
  2. Program management staff presented the quarterly Program Management Change Report on change orders over $500,000, covering December 1st through February 28th.3:51
  3. Item 13 was announced as a receive and file, and the committee moved to item 14, Office of the Inspector General construction change order spot checks.13:07
  4. Presenters from the Office of the Inspector General gave their quarterly spot check report on four change orders, including the Purple Line Extension and the G Line.13:51
  5. Item 14 was received and filed, and the committee took up item 15, the Caltrans quarterly report.31:27

No official identified

Transcribed, but no official’s voice was identified with enough confidence to show it.

Public comment: 0 speakers.

How we count

Each summary sentence is checked against the transcript before it is published; in a blind check, 98 of 100 sentences were right. A voice gets an official’s name only when two AI readers and a code check agree, so the minutes undercount and are not attendance. Officials only: members of the public are counted, never named, shown or quoted, and full transcripts aren’t published because they can carry their names. More on how we know